" Owner shall be at liberty, after three days written notice to the Contractor , to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the Contractor under... "
Michigan Reports: Cases Decided in the Supreme Court of Michigan - Seite 225
von Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1898
Vollansicht - Über dieses Buch

Michigan Reports: Cases Decided in the Supreme Court of Michigan, Band 200

Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1919 - 806 Seiten
...the architect, the owners shall be at liberty, after three days' written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure...
Vollansicht - Über dieses Buch

Michigan Reports: Cases Decided in the Supreme Court of Michigan, Band 187

Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1916 - 804 Seiten
...certified by the architect, the owner shall be at liberty after 48 hours' written notice to the contractor to provide any such labor or materials and to deduct...money then due, or thereafter to become due, to the contractor, under the contract, and if the architect shall certify that such refusal, neglect or failure...
Vollansicht - Über dieses Buch

Reports of Cases Heard and Determined in the Supreme Court ..., Band 68;Band 75

Marcus Tullius Hun - 1893 - 724 Seiten
...part herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three days' written notice...become due to the contractors under this contract. And if the architect shall certify that such refusal, neglect or failure is sufficient ground for such...
Vollansicht - Über dieses Buch

The Northwestern Reporter, Band 186

1922 - 1138 Seiten
...by the architect, the owner shall be at liberty, after three days' written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract, and if the architect <f;=For other cases see same topic and KEY-NUMBER...
Vollansicht - Über dieses Buch

The Pacific Reporter, Band 119

1912 - 1170 Seiten
...the architect, the owner shall be at liberty after five days (5) written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract ; and If the architect shall certify that such refusal, neglect or failure...
Vollansicht - Über dieses Buch

The Pacific Reporter, Band 140

1914 - 1230 Seiten
...liberty, after three days' written notice to the contractors, to provide all such labor or materials and deduct the cost thereof from any money then due or thereafter to become due the contractors under this contract ; and if the architects shall certify that such refusal, neglect...
Vollansicht - Über dieses Buch

The Pacific Reporter, Band 133

1913 - 1236 Seiten
...written notice to the contractor, to provide any such labor and materials, and to deduct the costs thereof from any money then due, or thereafter to become due, to the contractor under this contract ; and If the architects shall certify that such refusal, neglect, or...
Vollansicht - Über dieses Buch

The Northeastern Reporter, Band 39

1895 - 1150 Seiten
...part herein contained, such refusal, neglect, or failure being certified by the architect, the owner shall be at liberty, after three days' written notice...become due to the contractors under this contract; and, if the architect shall certify that such refusal, neglect or failure is sufficient ground for...
Vollansicht - Über dieses Buch

Atlantic Reporter, Band 67

1908 - 1134 Seiten
...the architects, the owner shall be at liberty, after three days' written notice to the contractor, to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract ; and If the architects shall certify that such refusal, neglect, or...
Vollansicht - Über dieses Buch

The Atlantic Reporter, Band 70

1908 - 1148 Seiten
...certified by the architect, the owner shall be at liberty after ten days' written notice to the contractor to provide any such labor or materials, and to deduct...money then due or thereafter to become due to the contractor under this contract. And, If the architect shall certify that such refusal, neglect, or...
Vollansicht - Über dieses Buch